英语翻译1.1 Seller shall furnish to the Expeditor/Buyer of the p

来源:学生作业帮 编辑:作业帮 分类:综合作业 时间:2024/10/06 10:18:10
英语翻译
1.1 Seller shall furnish to the Expeditor/Buyer of the purchaser,no later than four (4) weeks after the purchase order commitment an initial Project Schedule with purchasing,fabrication,inspection,and testing plans based on data available at that time and expanded upon throughout the design and fabrication cycle for each unit.
The above Project Schedule is to be submitted with a Progress Report in hard copy and is also required to be submitted at the same time,electronically.
The Project Schedule shall be detailed and should include the following applicable points.Typical schedule format is attached.Formatted by Day-Month-Year.
- Drawing Submittal Schedule
- Materials purchase and delivery of key components buyouts indicating components Purchase Order Number,Supplier Name & Contact information.
- Manufacturing/fabrication as applicable:
- Layout
- Fit-up and welding activities
- Witness inspections,or in process inspections
- Assembly
- Testing
- Cleaning/painting
- Preparation for shipment
- Delivery Point & date
1.2 Seller shall furnish to the Expeditor/Buyer,a summary of prior week activities & weekly progress reports covering the current status of all engineering,Purchasing,and fabrication functions and a forecast summary of work to be performed in the upcoming week.
Each report shall be in sufficient detail to allow a realistic evaluation of Seller's progress.In addition to by-weekly progress reports,the seller shall,on request of the purchaser,submit irregular reports with full information and within period as specified in the purchaser’s request from time to time,may covering but not limit to following:
A.Charts and detailed descriptions of progress,including each stage of design,material purchasing,fit up,welding,assembly,testing,surface cleaning/painting,packing,and delivery status;
B.Photographs showing the status of manufacture,packing,and delivery status;
C.For Manufacturing/fabrication (for each component/subassembly),the name of the manufacturer,manufacture location,percentage progress,and the actual or expected dates of Commencement of manufacture.
D.Preparation for shipment
E.Copies of test results and certificates of materials (MTR); for the raw material purchased,there shall be tracking numbers,such as heat No,lot No.to facilitate checking against MTR;
F.Comparisons of actual and planned progress,with details of any events or circumstances which may jeopardize the delivery schedule,the Seller shall take measures to maintain the schedule.
.1卖方应提供的Expeditor的/买方的购买者,不迟于4(4)周后,采购订单的承诺与采购,制造,检验一个初步的项目进度和测试计划,根据当时的数据后,可扩大整个设计和制造周期的每个单位.上述项目预期将于copy硬提交一份工作进度报告,也必须是在同一时间提交,电子.项目附表应详细,应包括以下内容适用点.Typical schedule format is attached.典型的时间表格式附后.Formatted by Day-Month-Year.- Drawing Submittal Schedule - Materials purchase and delivery of key components buyouts indicating components Purchase Order Number,Supplier Name & Contact information.- Manufacturing/fabrication as applicable:- Layout - Fit-up and welding activities - Witness inspections,or in process inspections - Assembly - Testing - Cleaning/painting - Preparation for shipment - Delivery Point & date 1.2 Seller shall furnish to the Expeditor/Buyer,a summary of prior week activities & weekly progress reports covering the current status of all engineering,Purchasing,and fabrication functions and a forecast summary of work to be performed in the upcoming week.Each report shall be in sufficient detail to allow a realistic evaluation of Seller's progress.由日格式化个月大的年份.-绘图送件进度-材料采购和:主要适用部件交付收购显示部件跟采购订单编号,供应商名称及资料.-加工制造业/因为-布局-装修和焊接活动-证人检查,或在检查过程-装配-测试-清洗/画-准备装运-送货点和日期1.2卖方应提供的Expeditor的/采购,进度总结前一周的活动及每周报告涵盖了所有的当前状态工程,采购和制造功能和预测工作进行总结,将在即将到来的一周.每份报告的细节将在足以使一个进步的现实评价卖方.In addition to by-weekly progress reports,the seller shall,on request of the purchaser,submit irregular reports with full information and within period as specified in the purchaser's request from time to time,may covering but not limit to following:A.除了由每周进度报告,卖方应根据买方要求的,不规则的时间内提交的全部资料和报告期间所指明的要求购买者的时间,可能包括但不限于如下:A.Charts and detailed descriptions of progress,including each stage of design,material purchasing,fit up,welding,assembly,testing,surface cleaning/painting,packing,and delivery status; B.图表和进度的详细说明,包括每个设计阶段,材料采购,装修,焊接,装配,测试,表面清洗/绘画,包装,交付状态;乙 Photographs showing the status of manufacture,packing,and delivery status; C.照片显示的制造地位,包装,交付状态;长 For Manufacturing/fabrication (for each component/subassembly),the name of the manufacturer,manufacture location,percentage progress,and the actual or expected dates of Commencement of manufacture.D.制造/装配组件(每个/组件),进度制造商名称,生产地点,比例和日期的年份生产实际或预期.四 Preparation for shipment E.装运准备大肠杆菌 Copies of test results and certificates of materials (MTR); for the raw material purchased,there shall be tracking numbers,such as heat No,lot No.to facilitate checking against MTR; F.)副本测试结果和证书材料(地铁,为购买原料时,应当以热追踪号码,如没有,批号,以方便地铁核对;楼 Comparisons of actual and planned progress,with details of any events or circumstances which may jeopardize the delivery schedule,the Seller shall take measures to maintain the schedule.实际的和计划进度的比较与任何事件或情况的细节,这可能危及交货计划,卖方应采取措施,保持时间表.